Front End Loading (FEL-3): How to Ensure the Project is Ready for Funding and Execution

FEL 3 engineering execution prep

By this time, you’ve answered two important questions:

  • Is this the right project to pursue?
  • Have we selected the best solution?

Now comes the biggest question of all: Are we ready to execute? At the end of the FEL-3 phase, full capital funds are allocated, and the project proceeds to detailed design and construction. FEL-3 provides an opportunity to confirm that the project is truly ready before significant capital funds are committed. An engineering partner will use this phase to test assumptions, validate schedule constraints, and confirm that the owner has the information needed to execute with confidence.

1. Is the Project Scope Truly Defined?

One of the leading causes of cost overruns is changing scope after execution begins. Before moving into procurement or construction, ask your engineering partner:

  • Have project requirements been fully documented?
  • Are project boundaries clearly defined?
  • Have assumptions from FEL-2 been validated?
  • Are there any known scope gaps that still need to be resolved?

If the scope is still evolving significantly, the project probably isn’t ready for execution.

2. Can We Trust the Cost Estimate?

The FEL-3 project cost estimate should provide a much higher level of confidence than the early planning numbers developed during FEL-1 and FEL-2. Often this sets the total project budget, and any uncertainty or insufficient contingency could interfere with project success. It is worth understanding the overall level of confidence in the project estimate. Some discussion points to review at this stage are:

  • What assumptions and remaining risks could still impact cost?
  • Where is contingency being applied to cover the recorded unknowns?
  • Are schedule constraints and lead times accounted for?

A good engineering partner will explain the assumptions behind the cost estimate to show not only what the project is expected to cost, but also why.

3. Has Constructability Been Evaluated?

A design that works on paper needs to be practical to build and operate. During FEL-3, experienced engineering teams work closely with construction managers and operations personnel to identify possible challenges before work begins.

A constructability review during the FEL-3 phase can help determine how the project can be built safely and efficiently. An engineering partner should always consider and recommend opportunities to simplify construction and reduce downtime and disruptions to ongoing operations. Identifying and planning for these issues during the FEL-3 design phase is far less expensive than addressing them in the field.

4. Have Operations and Maintenance Been Included?

Projects are often judged by how well they perform years after construction. A project can be on budget and on schedule, but if the scope has missed the mark, it will not be considered a success. Often the people who operate the facility will have valuable perspectives on the details required for the project to remain successful after the project team has completed their work. In the FEL-3 phase it is important to confirm:

  • Is equipment accessible for maintenance?
  • Have operators reviewed the design?
  • Will this solution improve long-term reliability?
  • Are there operational concerns that still need to be addressed?

The people who will operate the facility should have a voice before the project moves forward.

5. Do We Understand the Remaining Risks?

Every project carries risk, but by the end of FEL-3 there should be very few surprises left. Your engineering partner should be able to identify remaining technical risks and regulatory requirements as well as explain how those risks will be managed during execution.

At the same time, understanding potential schedule risks will ensure that the execution plan is realistic, building confidence that the project can be delivered as expected. The following questions should be asked when making an execution plan:

  • Is the proposed schedule achievable?
  • Are there any procurement challenges or long-lead equipment concerns?

Is adequate construction staging space available, and are sufficient contractor resources available?A thorough understanding of remaining risks provides confidence in the project deliverables and establishes a path to success in the execution phase.

The Best Time to Find Problems Is Before Construction

The greatest value of FEL-3 is in reducing uncertainty before execution begins. Projects that enter construction with clearly defined scope, realistic schedules, reliable cost estimates, and a well-developed execution strategy are far more likely to stay within budget, on schedule, and achieve their intended business outcomes.

A Successful FEL Process Leads to Better Projects

Each phase of the Front End Loading process builds on the one before it. By treating each phase as a decision stage gate, the owners are able to manage project risks, improve capital allocation, and create a pathway for successful project delivery. The projects that perform best in the field are usually the ones that spent the most time asking the right questions before construction ever began.

  • FEL-1 helps owners determine whether the project is worth pursuing and identifies the best solution.
  • FEL-2 establishes a more detailed project scope and identifies project risks.
  • FEL-3 confirms the project is truly ready for execution.

Read more in the series:

Marina Poluektova headshot
Marina Poluektova

Process Engineer

See profile

SIGN UP FOR OUR NEWSLETTER

Join our email list!

By clicking Sign Up you’re confirming that you agree with our Terms and Conditions.